A 30.5-metre over-rail bridge has been proposed near the new Pahur railway station as part of the Jalgaon–Jalna railway line project, according to a report by Loksatta.
The bridge is planned where the proposed Jalgaon–Jalna route will cross the Pachora–Jamner–Bodwad railway line. The structure is intended to allow both railway routes to operate without the conflicts that can arise from a level crossing, the report said.
The proposed railway line will begin at Bhadli station on the Jalgaon–Bhusawal route and pass close to the new Pahur station. The location of the bridge will therefore be an important part of coordinating the two railway corridors, according to the report.
The 174-kilometre Jalgaon–Jalna project is estimated to cost about ₹7,106 crore. Land acquisition for the project is reportedly nearing completion, while preliminary work has begun in and around Jalgaon before track-laying starts.
The project is intended to provide a direct rail connection between North Maharashtra and Marathwada. Loksatta reported that the route would reduce the existing rail distance between Jalgaon and Jalna from about 336 kilometres to 174 kilometres.
The report also said the project will include a proposed 23.5-kilometre tunnel, described as the country’s largest traffic tunnel. The tunnel and the over-rail bridge are among the major structures planned along the route.
The Jalgaon–Jalna line remains a proposed infrastructure project. The reported progress relates to land acquisition, preliminary activity and design provisions for crossings; the report does not establish a completion date or the start of train services.