The Japan International Cooperation Agency (JICA) has approved the revised detailed project report (DPR) for the 27.34-km Singaperumal Koil-Poonjeri section of Chennai’s Peripheral Ring Road, clearing the way for fresh tenders, according to The New Indian Express.
The section, identified as Phase 5 of the 133-km Chennai Peripheral Ring Road (CPRR), is planned as an access-controlled six-lane highway with two-lane service roads on either side. Its estimated cost is between Rs 2,900 crore and Rs 3,015 crore.
The Tamil Nadu Road Development Company (TNRDC) cancelled the earlier tender on September 17, citing administrative reasons. The report said the tender was cancelled after the project authorities received official flood-level data from the Water Resources Department (WRD), which indicated that the proposed carriageway height needed to be revised.
A senior government official told the publication that the earlier DPR had been prepared without obtaining the WRD’s official flood-level data. The official said the data reached TNRDC during the tendering process and led to changes in the required carriageway height.
The DPR was subsequently revised to incorporate those changes. JICA officials recently scrutinised and approved the revised document, the official said, adding that fresh tenders are expected to be invited shortly. The report does not provide a specific date for the new tender.
The revision places flood-level information at the centre of the project’s next stage. For a major road planned across Chennai’s wider metropolitan region, the carriageway height affects construction requirements and the highway’s ability to remain usable during flooding. In this case, the need to revise the DPR also shows how the availability and timing of official hydrological data can influence procurement and project schedules.
The Tamil Nadu government is developing the CPRR at an estimated overall cost of Rs 17,000 crore. The planned road begins at Ennore Port and terminates at Poonjeri near Mahabalipuram on the East Coast Road. It passes through Thatchur, the Tiruvallur Bypass, Sriperumbudur and Singaperumal Koil.
The project is intended to decongest Chennai’s roads and improve the movement of goods from Ennore and Kattupalli ports, as well as from Andhra Pradesh to different parts of Tamil Nadu. Its funding is being provided by JICA, the Asian Development Bank and the state government.
Phase 1 comprises the 25.4-km Northern Port Access Road between Ennore Port and Thatchur on the Chennai-Kolkata National Highway, along with a link road to the Chennai Outer Ring Road. Phase 2 is planned between Thatchur and the Tiruvallur Bypass, while Phase 3 connects the Tiruvallur Bypass with Sriperumbudur. The report said these phases are under construction.
For Phase 5, the immediate next step is the issue of a fresh tender following JICA’s approval of the revised DPR. The available report does not state whether the revised flood assessment will alter the project’s final cost, construction schedule or land-related requirements.