Uttarakhand Chief Minister Pushkar Singh Dhami has directed officials to accelerate infrastructure works under the Haridwar Ganga Corridor and set a December target for completing the works currently covered by the programme, the Press Trust of India reported after a review meeting in Dehradun on Friday.
The fifth meeting of the Uttarakhand Investment and Infrastructure Development Board (UIIDB), chaired by Dhami, reviewed the physical and financial progress of projects under the Haridwar Ganga Corridor, the Rishikesh Ganga Corridor and the Sharda Riverfront Corridor.
According to information shared at the meeting, projects worth Rs 8,279 crore have been proposed across the three corridors. Projects valued at about Rs 1,109 crore are currently under implementation. The state government estimated that the wider programme could generate direct employment for 21,000-27,000 people and indirect employment for 45,000-53,000 people.
Under the Haridwar Ganga Corridor, projects worth Rs 3,297 crore have been proposed, with projects valued at about Rs 495 crore in the implementation phase. The administrative route was reported to be 75 per cent complete, while development works in the northern area of Har Ki Pauri were 70 per cent complete.
Redevelopment of Har Ki Pauri and Subhash Ghat was reported to be 50 per cent complete, while work in the Rodi Belwala area had reached 45 per cent. Dhami instructed officials to accelerate ongoing works and complete the formalities needed to start new projects. He also asked departments to ensure visible progress on certain projects within the following month.
The Rishikesh Ganga Corridor has proposed projects worth Rs 3,456 crore, of which projects valued at Rs 274 crore are under implementation. Construction of an Integrated Command and Control Centre near Janki Jhula was reported to be 39 per cent complete, with completion targeted for June 2027.
Other works listed for Rishikesh include development of Triveni Ghat at a cost of Rs 115.07 crore, beautification of the Aastha Path at Rs 35.78 crore and construction of the Chandrabhaga pedestrian bridge at Rs 32.28 crore. The meeting also reviewed efforts to develop rafting and tourist facilities in the Shivpuri and Neem Beach areas.
Under the Sharda Riverfront Corridor, projects worth Rs 1,526 crore have been proposed, with projects valued at Rs 340.49 crore in the implementation phase.
Dhami said development should account for the local identity, culture, religious significance and natural characteristics of each region. He called for coordination among departments so that the corridor projects support tourism and employment while reflecting local conditions.