India’s ongoing central infrastructure projects have recorded a cumulative cost overrun of around Rs 3.28 lakh crore, with their combined revised estimate rising to Rs 38.11 lakh crore, according to the Ministry of Statistics and Programme Implementation’s (MoSPI) monthly report for October 2026.
The report covers 1,862 projects costing Rs 150 crore and above across 17 central ministries and departments. Their original estimated cost was Rs 34.82 lakh crore, which has increased to Rs 38,11,292 crore. MoSPI did not disclose the exact number of projects that had exceeded their original cost estimates.
Total expenditure on the projects has reached Rs 17.87 lakh crore, equivalent to 46.88% of their revised estimated cost. The data shows that 649 projects, or about 35% of the total, have achieved more than 80% physical progress. By comparison, 326 projects, or 18%, have crossed 80% financial completion.
MoSPI said the projects were at different stages of implementation. Among projects nearing completion, physical progress was higher than financial progress, while financial progress was relatively higher during the initial stages. The report attributed the latter pattern to upfront expenditure during project implementation.
Transport and logistics account for the largest share of the monitored pipeline, with 1,324 projects having a combined revised cost of Rs 20.37 lakh crore. The Ministry of Road Transport and Highways has the highest number of projects, at 972, representing 52% of the total. Their combined revised cost stands at Rs 9.55 lakh crore, or 25% of the overall project cost.
The Ministry of Railways is implementing 288 projects with a revised cost of Rs 7.38 lakh crore. The Ministry of Coal accounts for 121 projects worth Rs 2.22 lakh crore, while the Ministry of Petroleum and Natural Gas has 117 projects valued at Rs 4.42 lakh crore. The Ministry of Power’s 108 projects have a revised value of Rs 6.55 lakh crore.
The Ministry of Housing and Urban Affairs is implementing 50 projects with a combined revised cost of Rs 3.44 lakh crore. The Department of Water Resources, River Development and Ganga Rejuvenation has 33 projects worth Rs 1.93 lakh crore.
The monitored pipeline includes 790 mega projects costing Rs 1,000 crore or more and 1,072 major projects costing less than Rs 1,000 crore. The remaining 173 projects, accounting for 9% of the total, have a combined cost of Rs 2.63 lakh crore and are spread across departments including higher education, civil aviation, steel, telecommunications, ports, shipping and waterways, health, mines and sports.
The report’s figures highlight the scale of revised financial commitments across India’s central infrastructure programme. However, the available data does not identify the causes of individual cost increases or establish how many projects are responsible for the cumulative overrun. Those details would be necessary to assess whether escalation is concentrated in a smaller group of projects or distributed across the pipeline.