TGRERA orders Hyderabad builder to complete Adibatla project

The Telangana Real Estate Regulatory Authority (TGRERA) has ordered ELV Projects Pvt Ltd to complete pending work at its ELV Cosmopolis project in Adibatla, near Hyderabad, within six months, according to a report by Siasat.

The authority directed the developer to make the lifts operational, arrange water and power backup, clear electricity dues for common areas and ensure uninterrupted power for flats and shared facilities. The order also covers the completion of rainwater-harvesting pits, a children’s play area, a swimming pool and sports facilities.

The directions followed complaints from buyers about repeated power cuts caused by pending electricity bills. Buyers also said they had paid Rs 50,000 per flat for a water connection but had not received municipal water supply. Other complaints concerned the generator and parking facilities.

TGRERA member K Srinivasa Rao found that the project remained incomplete, promised amenities had not been delivered and the developer had not obtained an occupancy certificate, the report said. The developer has been given three months after completing the work to obtain the occupancy certificate.

In a separate case, TGRERA fined Aliens Developers Pvt Ltd Rs 2 crore over collections from buyers of a flat in the Aliens Space Station Township project in Tellapur. The authority held that the developer had taken more than 10 per cent of the flat’s price without a registered sale agreement.

A Nagalakshmi and V Nagarjun Yadav booked a 1,412-square-foot flat in October 2022 for Rs 1 crore before taxes. They paid Rs 40 lakh towards the flat and Rs 1.9 lakh for interiors. The project was registered in November 2023, while the developer continued collecting money until August 2025, according to the report.

The draft agreement received by the buyers on September 6, 2025, promised possession within 19 months after payment of half the price, with an additional 12-month grace period. It cited material shortages and contractor disputes as reasons for delay.

Under the order, the buyers may opt out of the purchase. If they do so, the developer must refund Rs 42 lakh without deductions within 60 days and pay interest at 10.85 per cent a year from the respective payment dates.