The proposed Shiv Murti-Ambience Mall flyover is intended to separate traffic entering Gurugram from the Dwarka Expressway from vehicles already travelling towards the city on NH-8, according to a report by The Times of India cited by Livemint. The National Highways Authority of India is expected to finalise the detailed project report within a month.
The planned elevated corridor would run for about 2.7 km from the Shiv Murti interchange in Delhi to a point opposite Ambience Mall in Gurugram. It is proposed as a three-lane flyover beginning after the exit ramp of the existing right-turn underpass at the Dwarka Expressway interchange.
The interchange currently requires vehicles emerging from the underpass to merge with traffic travelling from Delhi towards Gurugram. According to the report, this movement slows traffic during peak periods and contributes to queues on the approach to the city.
NHAI’s traffic assessment rated the stretch, including its service road, at “Service F” during peak hours. In level-of-service classifications, the grade denotes severe congestion. The report linked the increased pressure at the interchange to the opening of the Dwarka Expressway, which has added traffic to an already heavily loaded section of NH-8.
Under the proposed arrangement, vehicles exiting the existing underpass would be channelled onto the elevated corridor, while traffic already using NH-8 would continue on the main carriageway below. The two traffic streams would therefore remain separate for the relevant section instead of converging at the interchange.
The corridor is planned along the space currently occupied by the surface drain between the main carriageway and the service road. It would cross into Gurugram and terminate opposite Ambience Mall. An exit ramp is proposed near the approach to the existing Rajokri flyover, allowing motorists to reach the service road serving Ambience Mall, Cyber City and Udyog Vihar.
Vehicles travelling farther into Gurugram would continue along the elevated section before rejoining the main carriageway, according to the report. The stated objective is to give traffic arriving from the Dwarka Expressway a dedicated route while reducing disruption to vehicles already travelling on NH-8.
An NHAI official said the DPR was at an advanced stage, with the design prepared and under examination by a committee. Once finalised, the proposal will be submitted to the Union ministry for approval. The project’s estimated cost has not yet been worked out.
The proposal is also being planned alongside a separate project near Ambience Mall being undertaken by DLF. In October, NHAI granted in-principle approval for a flyover along the service road and a right-turn underpass beneath the expressway, the report said. DLF has finalised an agency for that work, with construction expected to begin after the traffic police approve its traffic management plan.
NHAI has issued a no-objection certificate for the DLF flyover near Ambience Mall and intends to expedite the project so that the two structures can be completed simultaneously, the official said. Coordination between the schemes is intended to address the bottleneck around the Ambience Mall interchange and improve movement between Delhi and Gurugram.
The immediate significance of the NHAI proposal is that it seeks to resolve a merging problem through traffic separation rather than by adding another general-purpose lane to the existing carriageway. However, the project remains at the DPR and approval stage. Its cost, construction timeline, final design, land and utility implications, and the arrangements required to manage traffic during construction have not been disclosed in the report. The effectiveness of the corridor will also depend on how its ramps connect with the existing Rajokri, Shiv Murti and Ambience Mall approaches and how the proposed NHAI and DLF works are sequenced.