Karnataka has formally shelved its proposal to acquire about six acres of Bengaluru’s Lalbagh Botanical Garden for the North-South Tunnel Road, forcing a change in the proposed alignment of the 17.6-km project. Bengaluru Smart Infrastructure Ltd (B-SMILE) is now examining alternative sites for the road’s entry and exit ramps.
Greater Bengaluru Development Minister Krishna Byre Gowda confirmed the change while speaking to reporters on Wednesday. He said the new alignment would remain away from Lalbagh and that officials were surveying different locations before taking a final decision.
Two possible sites have emerged in the preliminary survey. One is land belonging to the Karnataka State Road Transport Corporation near its headquarters in Shanthinagar. The other is a vacant parcel within the premises of the Rajiv Gandhi Institute of Chest Diseases, near the National Institute of Mental Health and Neuro-Sciences. B-SMILE officials have not confirmed either location, saying both remain under consideration.
The tunnel road is planned to connect Hebbal with Central Silk Board Junction. The Congress-led state government had proposed it as a way to address traffic congestion while avoiding the high cost and difficulty of acquiring land for surface road widening. The project has nevertheless faced objections over its environmental impact, mobility benefits and financial viability.
The proposed use of Lalbagh land triggered a citizen protest at the historic botanical garden. The decision to move the alignment removes the immediate land-acquisition pressure on Lalbagh, but it does not settle the larger questions around the tunnel road’s design, cost or transport priorities. Any new ramp location will still need to be assessed for land ownership, access, construction effects and its relationship with surrounding roads and public institutions. The report does not provide the results of those assessments.
The project’s cost also remains under discussion. Byre Gowda said a committee led by the chief secretary had held two rounds of meetings with the Adani Group firm that emerged as the lowest bidder for construction. The committee includes senior officials from the Finance and Public Works departments and is negotiating to reduce the quoted price.
The government has indicated that users could be charged more than Rs 300 for a one-way journey across the tunnel to help recover costs. That proposed toll has contributed to questions about who would be able to use the facility and whether the project would provide broad congestion relief or mainly serve motorists willing to pay for a faster route. The available report does not provide a traffic forecast, a final cost or a completed financial assessment.
Bengaluru South MP L S Tejasvi Surya, who led the protest against using Lalbagh land, described the decision as an initial victory for citizens opposing what he called an unscientific and unnecessary project. He also said that changing the alignment did not resolve his opposition and alleged that the tunnel road was affecting the expansion of Namma Metro’s Red Line. He referred to the dropping of the Veterinary College station and criticised delays in Metro approvals. These comments were made by Surya and were not independently substantiated in the report.
The immediate next step is therefore a further survey rather than construction at a confirmed alternative site. B-SMILE has yet to select the location of the ramps, the state government is still negotiating the project price, and opposition to the tunnel road continues. Moving the project away from Lalbagh addresses one prominent public-land dispute, but the final alignment, cost, toll structure and coordination with mass-transit plans remain unresolved.