HomeBreaking NewsMumbai Metro 11 Survey Covers 800 Structures Along Proposed Route

Mumbai Metro 11 Survey Covers 800 Structures Along Proposed Route

Mumbai Metro Rail Corporation (MMRC) has begun a baseline socio-economic survey of around 800 buildings and structures that could be affected by the proposed Metro Line 11 between Wadala and the Gateway of India.

The survey is being conducted by Socioquest Solutions, an agency appointed by MMRC, to document properties and the socio-economic profile of their occupants before implementation of the 17.5-km underground corridor. The exercise will include property measurements, photography and videography.

MMRC’s Rehabilitation and Resettlement Department issued a public notice asking property owners and occupants of potentially affected structures to cooperate with authorised survey representatives. Residents have been asked to keep original documents and photocopies ready for verification.

The documents listed in the notice include Aadhaar cards, electricity and water bills, property tax receipts, property cards, rent receipts, rent agreements, ration cards, Index-II documents, occupancy certificates and business licences. The information is intended to establish property and occupancy details as part of the project’s rehabilitation and resettlement groundwork.

Residents seeking further information have been directed to MMRC’s Coordination Committee office near the Suburban Collector’s Office. The report does not specify a completion date for the survey or set out rehabilitation terms for individual properties.

The proposed corridor is planned to have 14 underground stations at Anik Depot, Wadala Depot, CGS Colony, Ganesh Nagar, BPT Hospital, Shivdi, Haji Bunder, Darukhana, Byculla, Nagpada Junction, Bhendi Bazaar, CSMT Metro, Horniman Circle and Gateway of India.

The Maharashtra government decided in March to extend the proposed route by 6.9 km to Bandra Railway Terminus via Dharavi. Feasibility and related studies for that extension are yet to be completed, according to the report. The current survey description concerns the proposed Wadala–Gateway of India corridor.

The project is estimated to cost Rs 23,487 crore and is targeted for completion by August 2032. The first phase up to Wadala has received financial backing from the Japan International Cooperation Agency (JICA), which has agreed to provide an official development assistance loan of 92.4 billion yen, reported as approximately Rs 5,500 crore.

Once operational, the corridor is expected to improve east–south connectivity between Mumbai’s redeveloping port area and South Mumbai. It is also expected to provide another public transport link towards the eastern waterfront and improve access to Atal Setu from the city side.