Western Railway will impose an 80-day mega block at Surat station for redevelopment work, shifting the stoppages of 139 trains to Udhna and Utran, according to a report by Nav Gujarat Samay. The Railway Board has approved the plan, while the exact start date is expected to be announced within a week.
The work is part of the Multimodal Transportation Hub (MMTH) project at Surat station. Platform 1 will be dismantled and rebuilt, requiring 89 trains to stop at Udhna and 50 at Utran during the block. Forty-four trains, including Vande Bharat, Rajdhani and Shatabdi services, will continue operating from Surat’s Platform 2.
The changes will affect passengers travelling from Surat and those who normally board at the station’s Platform 1. Travellers using the shifted services will need to plan for access to Udhna or Utran and confirm the revised stoppage before departure. The report said passengers should rely on the final railway notification rather than the station shown on an older ticket or timetable.
The construction has been divided into four stages. During the first 10 days, facilities on Platform 1 will be removed and foundations for overhead equipment will be prepared. From the 11th to the 25th day, the platform, roof, shed, shops and water-supply structures will be dismantled, along with work on underground services.
Civil and structural work, including launching beams and columns for the concourse, is scheduled for days 26 to 62. The final 18 days will be used to complete pending work and restore the site.
Services listed for shifting include Gujarat Express, Avantika Express and other trains at Udhna, while Lokshakti, Saurashtra Mail and selected Rajdhani services are among those assigned to Utran. Vande Bharat, Shatabdi, Tejas Rajdhani and Double Decker services are among the trains reported to remain at Surat on Platform 2. Western Railway’s chief public relations officer said the start date would be fixed and communicated to passengers in advance.