The Nashik Municipal Corporation’s general body has approved two proposals worth Rs 372.5 crore to provide water supply and sewage infrastructure at Tapovan Sadhugram and other locations ahead of the 2027 Simhastha Kumbh Mela.
The approved works include a Rs 206 crore sewage collection and disposal system at Sadhugram and a Rs 166 crore water supply network serving Sadhugram, designated parking areas and routes expected to be used by pilgrims. The proposals were approved during the civic body’s general body meeting on Friday, with Mayor Himgauri Aher approving both measures, according to the Times of India report.
Under the sewage project, the civic body plans to lay about 120 km of temporary sewer lines across the Tapovan Sadhugram. The site is being developed over approximately 1,200 acres. The proposed network will use pipelines with diameters ranging from 200 mm to 600 mm and has been designed to handle around 110 million litres of sewage per day during the Kumbh.
The water supply project will cover the Sadhugram, designated parking areas and pilgrimage routes. Together, the two proposals are intended to support essential services at temporary and high-footfall locations associated with the event.
Funding for both projects is to be provided by the Nashik-Trimbakeshwar Kumbh Mela Authority. The approval establishes the proposed scope and funding source, while the report does not provide details on tendering, construction milestones, operating arrangements after the event or the treatment and disposal facilities linked to the temporary sewer network.
The scale of the planned sewage capacity highlights the service demands created by a large, temporary settlement. For Nashik, implementation will require the water and sanitation systems at Sadhugram, parking sites and routes to be coordinated with the wider city network as preparations for the 2027 Kumbh progress.