HomeAnalysisKalkere Lake’s Rs 10 Crore Revival Remains Stalled in Bengaluru

Kalkere Lake’s Rs 10 Crore Revival Remains Stalled in Bengaluru

Kalkere Lake in Bengaluru continues to face sewage inflow, excessive weed growth, foul odour and mosquito nuisance, while key works under a proposed Rs 10 crore rejuvenation project remain incomplete, according to residents and the Bengaluru East City Corporation (BECC).

The lake is used by residents of Lakedew Layout and nearby areas for morning and evening walks. Residents told Bangalore Mirror that the waterbody and the adjoining stormwater drain are affected by weeds, including water hyacinth, and persistent odour.

A board at the site states that desilting and other development works were to be completed within 11 months. However, residents said the project, which was awarded in 2022, has not progressed as expected. They said a contractor had been engaged to drain water from the lake more than a year ago, but desilting had not begun.

Mohan Raghavan, a resident, said the authorities should take up the developmental works for the benefit of people living around the lake. Dr C Radhakrishnan, a member of the LG Plot Owners Association and a Lakedew Layout resident, said the lake and adjoining drain were stinking and that the mosquito problem had become severe.

Residents also said that assurances had not translated into sustained work. One resident recalled that the then Executive Engineer, Arpita, visited the lake in February and assured them that the problems would be addressed. The resident alleged that authorities had been promising to rejuvenate the lake since 2022, with only short-term responses being undertaken.

BECC Executive Engineer (Lakes) Bhoopradha said desilting and de-weeding would be taken up after approval from higher authorities. She said diversion of sewage was in progress and that she would look into the matter.

The status of Kalkere Lake illustrates the gap between announcing an urban waterbody rejuvenation project and completing the work needed to restore its basic functions. Until sewage diversion, desilting and weed removal are carried out, residents are left dealing with an impaired public open space and an odour and mosquito nuisance.

Bangalore Mirror had previously reported on the lake’s condition on February 16, 2026, and on the proposed rejuvenation works on February 18, 2026. The latest account indicates that the project remains unresolved despite those earlier reports and assurances.