HomeAnalysisCourt exposes Bilaspur’s missing sewage plan for Arpa River

Court exposes Bilaspur’s missing sewage plan for Arpa River

The Chhattisgarh High Court has directed the Bilaspur Municipal Corporation to submit definite figures on the sewage treatment infrastructure needed to prevent untreated sewage from reaching the Arpa River, after the civic body could not state how many treatment plants were required.

A Division Bench comprising Chief Justice Krushna Ram Mohapatra and Justice Santosh Sharma raised the issue on Nov 17 while hearing a 2019 public interest petition, Arvind Kumar Shukla v State of Chhattisgarh, along with connected petitions filed in 2020 and 2023, according to a report by The Times of India.

The court was told that four sewage treatment plants (STPs) were currently operational and that two more were expected to be completed by the end of December 2026. The corporation’s counsel also referred to figures on the quantity of sewage being treated at the four functioning plants before discharge into the river.

However, the Bench said the central issue was not only the capacity of the existing plants but the total number of STPs required to treat sewage flowing through Bilaspur’s 17 nalas before it enters the Arpa. The August 26, 2026 affidavit cited during the hearing did not contain that information, the report said.

The matter took an unusual turn when neither the civic body’s counsel nor its Commissioner could provide a definite answer. At the Bench’s request, the Commissioner joined the hearing virtually. He attributed the lack of clarity to repeated changes in the Detailed Project Reports (DPRs), while assuring the court that an affidavit containing definite facts, figures and supporting documents would be filed before the next hearing.

The court has given the Commissioner two weeks to submit the affidavit. A copy is also to be served on the petitioners’ counsel and the other respondents. The case has been listed for Dec 10, 2026.

The proceedings place Bilaspur’s sewage network under scrutiny as a planning and implementation issue, rather than only a question of individual treatment-plant performance. The court’s demand for a complete account of sewage flows, treatment requirements and proposed infrastructure could provide a clearer basis for assessing whether the city’s current and planned STPs match the waste entering the river system.

The report also records that R S Baghel, president of the Bilaspur High Court Bar Association, told the court that he wished to raise further issues concerning the Arpa River at the next hearing. No further details of those issues were provided.


RELATED ARTICLES

Most Popular

Latest News