The Delhi government is planning an elevated corridor on the Mehrauli-Badarpur (MB) Road to ease congestion across South Delhi, with the proposed project comprising four flyovers covering about 8 km, according to officials cited by Live Hindustan.
The corridor is expected to improve traffic movement between Saket, Ambedkar Nagar, Khanpur, Sangam Vihar and Pul Prahladpur. The project is divided into four sections, although only two have received Cabinet approval while studies are under way for the remaining two.
The first section is a 2.41-km flyover between Saket G Block and Sangam Vihar. More than 50% of its work has reportedly been completed. It is being constructed by the Delhi Metro Rail Corporation (DMRC) above an underground metro line and is being described as an integrated flyover.
The second section would run 2.56 km between Maa Anandmayi Marg and Pul Prahladpur. Work has begun on this stretch and funding has been approved, officials said. The Delhi Cabinet approved Rs 1,471.14 crore in March 2026 for the two sections.
The Maa Anandmayi Marg-Pul Prahladpur section is facing difficulties related to land acquisition. The Public Works Department (PWD) has written to the Delhi Development Authority (DDA), seeking the transfer of the land required for the work, according to the report.
The third proposed section would connect Sangam Vihar with Maa Anandmayi Marg over 2.72 km. The fourth would cover 450 metres between Pul Prahladpur and Badarpur. Consultants have been appointed for both sections, and studies are in progress.
The government is also assessing the number of trees that may need to be removed for the projects. The detailed project report (DPR) for the overall plan is expected to be prepared by January 2027 and submitted for financial approval thereafter, the report said.
The reported lengths of the four sections add up to approximately 8.14 km, while the proposed corridor has been described as about 8 km. The available information does not specify a construction completion date, final approval for the two sections under study, the precise land parcels involved or the outcome of the tree assessment.
If taken forward as described, the project would add grade-separated road capacity along a heavily congested route. However, its eventual scope and implementation will depend on land availability, environmental clearances, studies and subsequent financial approvals.