The Telangana High Court has admitted a writ petition filed by 287 people seeking compensation for 208 structures they say were submerged by the Singoor Project in Sangareddy district.
Justice K Sarath took up the petition filed by Koniti Thukkaiah and 286 others. The petitioners have told the court that the structures are under the project’s waters but that the authorities have neither acquired them nor paid compensation.
They have challenged the alleged failure to begin acquisition proceedings and provide compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act. According to the petitioners, the inaction is illegal and arbitrary and violates principles of natural justice.
As interim relief while the case is pending, the petitioners have asked the court to direct the Engineer-in-Chief of the Irrigation and CAD Department to examine and act on a proposal to release about Rs 3 crore in compensation for the affected structures.
They said the Chief Engineer had forwarded the proposal in a letter dated May 3, 2024. The report does not state that the compensation has been approved or released.
The Singoor Project was built across the Manjira river and is one of the sources of drinking water for Hyderabad. It also supplies water for irrigation. The petition therefore brings together questions of land acquisition, compensation and the social impact of water infrastructure serving both the city and the wider Sangareddy region.
The court’s admission allows the petition to proceed, but the available report does not provide details of any final finding on the ownership claims, the alleged submergence or the requested interim relief.