HomeBreaking NewsPallikaranai construction freeze stays after Madras HC ruling

Pallikaranai construction freeze stays after Madras HC ruling

The one-kilometre restriction on construction around Chennai’s Pallikaranai marshland will continue after the Madras High Court directed petitioners challenging the freeze on development permissions to approach the Supreme Court.

The ruling means the Chennai Metropolitan Development Authority (CMDA) will not process fresh planning applications within the restricted zone around the Pallikaranai Ramsar site. Projects that have already received approvals can continue, according to CMDA member-secretary A R Rahul Nadh, who was quoted by The New Indian Express.

“Only projects that have already received approvals can continue. Fresh proposals cannot be processed,” Rahul Nadh said.

A bench comprising Chief Justice Sushrut Arvind Dharmadhikari and Justice G Arul Murugan passed the order while disposing of 13 petitions challenging a September 24, 2025, order of the National Green Tribunal (NGT). The petitions were filed by CREDAI Chennai, real estate developers, residents’ associations, trusts and individual landowners.

The NGT had directed the CMDA not to grant planning permissions within the Pallikaranai Ramsar site and its one-kilometre Zone of Influence until an Integrated Management Plan was finalised. The CMDA subsequently issued an order on October 9, 2025, freezing planning approvals and building permits across the marked area.

During the High Court proceedings, the Tamil Nadu State Wetland Authority submitted a revised proposal based on a scientific assessment by the National Centre for Sustainable Coastal Management. The proposal reduced the interim Zone of Influence from 3,474 hectares, or 8,584 acres, to 128.19 hectares covering 36 specific survey numbers.

The authority identified these survey numbers as areas directly affecting water inflow and drainage connectivity. It also proposed allowing regulated construction subject to environmental safeguards. The report did not state that the revised proposal had been accepted by the court or implemented by the CMDA.

CREDAI Chennai president Mehul H Doshi said the association was shocked by the outcome and would approach the Supreme Court immediately. He questioned why the petitioners had been directed to move to the Supreme Court after the State Wetland Authority had prepared a revised interim Zone of Influence.

Doshi also said the development freeze was affecting ongoing projects because banks were not releasing funds. The reported restriction therefore applies not only to new proposals but, according to CREDAI Chennai, is also creating financing difficulties for projects already under way.

The state’s submissions during the proceedings said the one-kilometre zone covers parts of 15 villages and that 84.2% of the area was already densely built up before Pallikaranai received Ramsar recognition in 2022.

For now, the CMDA’s position remains that fresh planning applications within the restricted zone cannot be processed. Any change to the restriction, including the proposed smaller zone or regulated construction framework, will depend on further proceedings and decisions by the Supreme Court and the relevant authorities.