The Maharashtra State Electricity Transmission Company Ltd (Mahatransco) has warned the Nashik Municipal Corporation (NMC) to maintain mandatory safety clearances from high-voltage transmission lines while raising and widening roads for the 2027 Simhastha Kumbh Mela.

In a letter to the civic body, Mahatransco said raising road levels beneath 132kV and 220kV extra-high-voltage transmission lines could reduce the vertical distance between live conductors and vehicles using the roads. It warned that tall container trucks and other heavy vehicles regularly pass beneath the lines, creating a risk of electrical flashovers, serious accidents, deaths and power disruptions if clearances are not maintained.

The utility identified stretches between Papaya Nursery and XLO Point near AJ Fitness Hub, Nandini Bridge and Satpur-Ambad Link Road, and Gangapur to Bardaan Phata and Sula Chowk as areas of concern.

Mahatransco said excavation or construction within 13.5 metres on either side of the centre line of a 132kV transmission line, and within 17.5 metres on either side of a 220kV line, is not permissible. It asked the NMC to preserve the required right of way and statutory clearances during road works.

The utility said it was conducting site inspections and preparing technical estimates for modifications to its transmission infrastructure. Where raising road levels is unavoidable, it asked the civic body to provide technically suitable alternative land for raising or relocating transmission towers.

Mahatransco said tower relocation could be difficult because several plots along the transmission corridors have been developed and some sections have densely populated settlements. It also said it had repeatedly sought documents from the NMC needed to prepare and approve technical estimates, but the information had not yet been submitted.

The utility said the safety requirements are mandatory under the Electricity Act, 2003, and the Central Electricity Authority (Measures Relating to Safety and Electric Supply) Regulations, 2023.

NMC officials said instructions had been issued to officials and contractors to take all necessary safety measures during the road works and remain in coordination with Mahatransco officials.