HomeBreaking NewsYadadri Power Plant Nears Full 4,000 MW Capacity After Delays

Yadadri Power Plant Nears Full 4,000 MW Capacity After Delays

Telangana’s Yadadri Thermal Power Station is moving towards full operation, with its fifth 800 MW unit expected to begin commercial generation in December and add to the state’s electricity supply. Four of the plant’s five units are already producing power, while the final unit was synchronised with the grid on October 20.

Located in Damaracherla mandal of Nalgonda district, the 4,000 MW Yadadri plant is operated by the Telangana Power Generation Corporation Limited (TGGENCO). The corporation is implementing an action plan to resolve technical problems in the coal-handling system before the fifth unit enters commercial operations.

TGGENCO officials said the plant’s main generation systems, including the boiler, turbine and generator, as well as its ash-handling and water-supply systems, are functioning satisfactorily. Technical issues in the coal-handling plant had affected the movement of fuel to the units, prompting inspections and a coordinated intervention involving TGGENCO, Bharat Heavy Electricals Limited (BHEL) and the state Energy Department.

Following directions from Chief Minister A. Revanth Reddy and Deputy Chief Minister Bhatti Vikramarka, a high-level team led by Energy Department Special Chief Secretary Vikas Raj and TGGENCO chairman and managing director Dr S. Harish conducted on-site inspections and formulated an action plan. Four coal-feeding lines have since been restored. Each line can supply an average of 800 tonnes of coal an hour, taking the plant’s coal-handling capacity to 3,200 tonnes an hour, according to the report.

The state has also arranged additional coal supplies to reduce the risk of interruptions. Three to four coal rakes are being transported daily from the Naini coal mine operated by Singareni Collieries Company Limited. About 4.26 lakh metric tonnes of coal have so far been moved from Naini to Yadadri.

Agreements have also been finalised to procure 4.6 lakh tonnes from Mahanadi Coalfields Limited and South Eastern Coalfields Limited through the Window-II auction mechanism. Fuel Supply Agreements with the companies were concluded on November 4, and transportation has begun.

For longer-term supply, the Standing Linkage Committee has approved the annual supply of 7.71 million metric tonnes of coal from Mahanadi Coalfields Limited and Eastern Coalfields Limited, both subsidiaries of Coal India Limited, for two Yadadri units. The arrangement is intended to address continuing concerns over coal availability and quality.

The plant’s progress follows delays linked to the Covid-19 pandemic, forest clearances, railway land issues and directions from the National Green Tribunal concerning environmental permissions. Environmental Impact Assessment studies and public hearings were completed afresh, and construction activities resumed in February 2024.

The latest operational figures indicate the plant’s growing contribution to Telangana’s grid. On November 11, the state recorded its highest-ever power generation of 6,088 MW, with Yadadri alone producing 2,754 MW. The fifth unit’s commercial operation will determine when the station can move closer to its full installed capacity, with TGGENCO’s immediate focus remaining on coal-handling reliability and uninterrupted fuel supply.